| Arahan kerja | Estet | Blok | Sasaran | Aktiviti | Kontraktor | Kuantiti | Kadar | Kos | Dokumen | Peringkat | Oleh | Dikemas kini |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| WO-0914-020240 | Bukit Serdang | OP-14 | Blok OP-14 | Rondaan | Kontraktor Dilantik | 82.40 ha | RM 45.00/ha | RM 3,708.00 | AK-20260914-020240-OP-14 | Draf | Sistem - ERPladang | 14/09/2026 02:02 |
| WO-0914-020254 | Bukit Serdang | OP-14 | Blok OP-14 | Rondaan | Kontraktor Dilantik | 82.40 ha | RM 45.00/ha | RM 3,708.00 | AK-20260914-020254-OP-14 | Draf | Sistem - ERPladang | 14/09/2026 02:02 |
| WO-0911-050659 | Ayer Hitam | OP-52 | Lot OP52-15 | Baiki jalan | Kontraktor Dilantik | 1.00 kerja | RM 2,500.00/kerja | RM 2,500.00 | AK-20260911-050659-OP52-15 | Draf | Sistem - ERPladang | 11/09/2026 05:06 |
| WO-0907-071241 | Keratong | RB-12 | Blok RB-12 | Baiki jalan | Kontraktor Dilantik | 1.00 kerja | RM 2,500.00/kerja | RM 2,500.00 | AK-20260907-071241-RB-12 | Draf | Sistem - ERPladang | 07/09/2026 07:12 |
| WO-0902-032305 | Selancar | OP-31 | Blok OP-31 | Membaja | Kontraktor Dilantik | 71.60 ha | RM 1,000.00/ha | RM 71,600.00 | AK-20260902-032305-OP-31 | Dikeluarkan | Penyelia - Penyelia Ladang | 02/09/2026 03:43 |
| WO-0902-033348 | Bukit Serdang | OP-14 | Blok OP-14 | Membaja | Kontraktor Dilantik | 82.40 ha | RM 1,000.00/ha | RM 82,400.00 | AK-20260902-033348-OP-14 | Diterima kontraktor | Kontraktor - Kontraktor Dilantik | 02/09/2026 03:39 |
| WO-0902-034317 | Bukit Serdang | OP-14 | Blok OP-14 | Rondaan | Kontraktor Dilantik | 82.40 ha | RM 45.00/ha | RM 3,708.00 | AK-20260902-034317-OP-14 | Draf | Sistem - ERPladang | 02/09/2026 03:43 |
| WO-0826-104 | Bukit Serdang | OP-14 | Blok OP-14 | Menuai | Gang Satria | 1,384.32 tan | RM 85.00/tan | RM 117,667.20 | AK-20260826-OP-14 | Sedang berjalan | Kontraktor - Gang Satria | 26/08/2026 11:00 |
| WO-0826-111 | Selancar | OP-31 | Blok OP-31 | Membaja | Kontraktor Bayu | 71.60 ha | RM 1,000.00/ha | RM 71,600.00 | AK-20260826-OP-31 | Disahkan | Penyelia - Penyelia Ladang | 26/08/2026 13:00 |
| WO-0826-118 | Ayer Hitam | OP-22 | Blok OP-22 | Merumput | Gang Meranti | 64.20 ha | RM 220.00/ha | RM 14,124.00 | AK-20260826-OP-22 | Sedang berjalan | Kontraktor - Gang Meranti | 26/08/2026 11:00 |
| WO-0826-120 | Keratong | RB-08 | Blok RB-08 | Rondaan | Gang Lateks 2 | 45.90 ha | RM 45.00/ha | RM 2,065.50 | AK-20260826-RB-08 | Dibatalkan | Penyelia - Penyelia Ladang | 26/08/2026 10:00 |